LOAD SHEDDING TO HIT PARTS OF LUSAKA FROM 07-19HRS

ZESCO Limited has announced that it will shut down electricity supply to parts of Lusaka which will necessitate interruption of power supply.

According to a notice by ZESCO Limited, the power supply interruption will affect Barlastone, Kanyama, Chinika, Industrial Area, Matero and surrounding areas.

The Utility firm says it will undertake maintenance works on the 132/33 kv transformer at Lusaka west substation which will necessitate loss of power supply from 07:00 to 19:00, tomorrow Tuesday, 24th May, 2022.

ZESCO has since cautioned customers to treat all supply lines as live, because power may be restored before the scheduled time.

About HeyMedia

HeyMedia is a digital social network platform dedicated to Zambians to showcase their latest news, culture, lifestyle, classifieds, music and politics. The platform also provides for different services such as news distribution for corporate entities, media and social media management, photography and videography, web management, graphic designing, music promotions and many other media relations.

Check Also

HH LUNGU RECONCILIATORY MOVE A NON STARTER WITHOUT PLAYERS

HH LUNGU RECONCILIATORY MOVE A NON STARTER WITHOUT PLAYERS Press Release 9th July 2024 Governance …

Leave a Reply

Your email address will not be published. Required fields are marked *